Project Overview

Integrated electrical power for a compact fishing vessel

Parkol Marine Engineering’s Green Isle newbuild, a 22.2-metre stern trawler, required a complete electrical generation and distribution system. The installation had to serve refrigerated seawater equipment, navigation, safety systems and everyday operation at sea within the vessel’s compact dimensions.

MJR designed, manufactured and installed the main and auxiliary distribution equipment, dedicated refrigerated seawater switchboard, harbour and shore power arrangements, and associated cabling and controls. Its work extended to onboard integration and functional testing, delivering a complete electrical power system certified to the applicable Marine Survey Office and Bureau Veritas standards.

Project significance

Electrical power serves both the vessel’s essential services and the refrigerated seawater cooling that protects the commercial value of the catch. Dedicated cooling distribution, protected essential supplies and controlled power transfer support the practical requirements of safe and reliable fishing operations.

The Challenge

Accommodating distribution equipment in a compact engine room

Limited engine-room space and vibration made switchboard layout an important design consideration. A complete generation and distribution system had to fit within a 22.2-metre vessel, so the arrangement of the boards and their interfaces with cabling and control equipment mattered alongside their electrical functions. Marine vibration was a further constraint on the layout of this onboard installation.

Maintaining power across different operational demands

The electrical system served loads with different operational roles: refrigerated seawater equipment supported catch preservation, while navigation and safety systems depended on reliable supplies. The requirement therefore extended beyond distributing power to individual loads. It also involved protecting essential services and managing the interfaces between vessel generation, harbour operation and shore power. These demands informed the use of segregated essential supplies, generator protection and controlled transfer arrangements.

Scope of Work

Switchboard design through to onboard integration

MJR’s scope combined design, manufacture and installation of the electrical distribution equipment with the onboard cabling, controls and integration work needed to connect the system.

  • Dual 400V main switchboards, with the main switchboard supply specified as 400VAC.
  • A dedicated refrigerated seawater switchboard.
  • Harbour and shore power arrangements.
  • 230V AC and 24V DC auxiliary distribution boards.
  • Associated cabling and control equipment.
  • Onboard installation, cable routing, termination, system integration and functional testing.

Solutions Delivered

Controlled connections between generation and shore power

The design combined interlocked bus-tie sections with no-break shore power transfer. Bus ties connect switchboard sections; interlocking constrains switching combinations to those permitted by the control design. No-break transfer is intended to maintain supply during a changeover. Together, these functions addressed the vessel’s need to manage electrical sources and distribution connections while supporting continuity of service between vessel generation and shore power.

Dedicated cooling distribution and segregated essential supplies

MJR provided a dedicated refrigerated seawater switchboard using corrosion-resistant enclosures. This gave the cooling equipment its own distribution board, with enclosure selection addressing resistance to corrosion. Refrigerated seawater cooling protects catch value, making its electrical supply an operationally important part of the trawler’s system rather than simply another auxiliary load.

The wider design also incorporated segregated essential supplies. Segregation separates designated essential circuits from other distribution paths, supporting the organisation and protection of services needed for vessel operation. On Green Isle, dedicated cooling distribution and protected essential services formed part of the architecture intended to support safe and reliable fishing operations.

Hardwired control with dedicated protection

Control relied on hardwired relay logic and dedicated protection units rather than PLCs. Relay logic implements control functions through wired relay contacts, while protection units monitor electrical conditions and initiate protective action when their configured criteria are met. The design included generator protection, giving the generation and distribution arrangement a dedicated protective function alongside its switching controls.

Delivery & Approval

Onboard installation, integration and certification

MJR worked at Parkol’s Whitby shipyard and the Port of Middlesbrough, UK. Its onboard responsibilities included installation, cable routing and termination, connecting the manufactured distribution equipment with the vessel’s electrical and control interfaces.

MJR completed system integration and functional testing. These activities brought the equipment and its connected controls together as a working electrical system. The electrical installation was certified to the applicable Marine Survey Office and Bureau Veritas standards.

Technical Summary

  1. Asset and application: Green Isle, a newbuild 22.2-metre stern trawler.
  1. Delivery locations: Parkol’s Whitby shipyard and the Port of Middlesbrough, UK.
  1. Main distribution: Dual 400V main switchboards; main switchboard supply specified as 400VAC.
  1. Cooling distribution: Dedicated refrigerated seawater switchboard with corrosion-resistant enclosures.
  1. Harbour and shore interfaces: Harbour and shore power arrangements; harbour generator rated at 40kVA.
  1. Auxiliary distribution: 230V AC and 24V DC distribution boards; auxiliary supplies specified as 230VAC and 24VDC.
  1. Switching and supply architecture: Interlocked bus-tie sections, no-break shore power transfer and segregated essential supplies.
  1. Control and protection: Hardwired relay logic and dedicated protection units, including generator protection; no PLC-based control.
  1. Installation and interfaces: Associated cabling and control equipment; onboard installation, cable routing, termination and system integration.
  1. Installation constraints: Limited engine-room space and vibration influenced switchboard layout.
  1. Testing and certification: Functional testing completed; electrical installation certified to the applicable Marine Survey Office and Bureau Veritas standards.

Project Outcomes

A complete, certified electrical power system

The project delivered a complete electrical power system for Green Isle, covering main and auxiliary distribution, refrigerated seawater distribution, harbour and shore power arrangements, and associated controls. MJR completed onboard installation, integration and functional testing, and the electrical installation was certified to the applicable Marine Survey Office and Bureau Veritas standards.

The resulting architecture supports the vessel’s operational requirements through dedicated cooling distribution, protected essential services and controlled transfer between vessel generation and shore power. These features are intended to support safe and reliable fishing operations, while the refrigerated seawater system serves the commercial purpose of preserving the catch’s value.

Table of contents
Planning a vessel automation project?

Share your vessel, equipment and interface requirements with MJR.

Related Services

Services to Support Your Project

From marine electrical design consultancy and engineering through construction, installation, commissioning, repair and testing, MJR supports the complete project lifecycle for newbuild, retrofit and upgrade projects.

product-image
Engineering & Construction

Integrated electrical power, switchboard, control and automation systems engineered, built and tested for demanding marine and offshore applications.

product-image
Consultancy & Design

Marine electrical design, FEED studies, calculations and system engineering developed around vessel, offshore and project requirements.

Related Solutions

Solutions for Your Operational Needs

Follow MJR project updates, company news and technical insight covering marine electrical engineering, automation, shore power, offshore vessel charging and vessel electrification.

solution-images
Power Generation & Distribution

Marine power distribution systems covering generation, switchboards, power management systems, load sharing, protection and electrical distribution.

Related Sectors

Sectors we are Powering

Follow MJR project updates, company news and technical insight covering marine electrical engineering, automation, shore power, offshore vessel charging and vessel electrification.

solution-images
Commercial Marine

Show how MJR designs, installs, commissions and supports product systems.

Related Projects

Relevant Project Experience

Explore MJR projects involving vessel automation, monitoring, control and power management across newbuild, retrofit and upgrade programmes.

No items found.
FAQ

Project questions

Questions and answers about Green Isle electrical power system.

What is the purpose of the interlocked bus-tie sections?

What role does generator protection perform?

Why was no-break shore power transfer included?

Why were essential supplies segregated?

Why did the refrigerated seawater equipment have a dedicated switchboard?

Was the control system based on PLCs?

Which electrical distribution voltages were provided?

What installation, testing and certification work was completed?