Project Overview

Modern controls for a historic passenger funicular

Saltburn Cliff Tramway is a historic water-balanced passenger funicular in Saltburn-by-the-Sea, North Yorkshire, UK. A major fire in January 2024 damaged its control system, prompting a replacement project within the wider restoration of the public passenger service.

Rapid Consulting engaged MJR Power & Automation to design and construct replacement control equipment across five stations. The arrangement combined PLC-based operation, a graphical operator console and industrial WiFi communications to both trams, bringing modern controls to the existing water-balanced installation.

Project significance

The work supported the return of an important local transport service and visitor attraction. Replacing communications associated with earlier service interruptions also aimed to protect the reliability of its continued passenger operation.

The Challenge

Coordinating five control stations

Five control stations had to operate as one coordinated system: the upper station, lower station, main control panel and individual panels for the Saltburn and Marske trams. The replacement therefore had to address the relationship between fixed stations and tram-mounted controls, rather than treat each panel as an independent replacement. These interfaces also had to work within the existing water-balanced tramway.

Replacing damaged controls for passenger operation

The replacement system was required to meet current functional safety requirements for the historic passenger railway. Restoring control equipment after the fire therefore involved more than reinstating ordinary operating functions: safety and emergency behaviour formed part of the engineering requirement alongside integration with the retained tramway.

Addressing communications interruptions

Radio communication faults had interrupted services before the fire. Replacing the damaged controls alone would not address that longstanding operational issue. Communications to both trams were consequently an important part of the replacement arrangement, linking the control-system upgrade to the reliability of passenger service.

Scope of Work

Replacement equipment across five stations

MJR’s scope for Rapid Consulting covered the design and construction of replacement control equipment. Its electrical and control-system work formed part of the wider restoration programme.

  • Replacement control equipment for five stations: the upper station, lower station, main control panel, Saltburn tram control panel and Marske tram control panel.
  • PLC-based operation and a graphical operator console.
  • Industrial WiFi communications to both trams, replacing the older unreliable radio link.
  • Additional safety and emergency functions, with the new control arrangements integrated into the existing water-balanced tramway.

Solutions Delivered

PLC-based operation within the existing tramway

The replacement arrangement used PLC-based operation within the existing water-balanced tramway. PLCs execute programmed control logic, providing a means of organising operating sequences and responses to inputs. For this project, PLC-based operation formed part of the approach to bringing five control stations together as one coordinated system while retaining the tramway’s water-balanced application.

A graphical interface for operators

A graphical operator console provided the operator-facing interface within the new arrangement. Graphical consoles present control information in a visual form to support an operator’s understanding of system status. The restored tramway’s improved operator visibility was a reported outcome, giving this interface a practical role beyond replacing damaged equipment.

Industrial WiFi to both trams

Industrial WiFi replaced the older unreliable radio link and provided communications to both trams. This addressed a known source of service interruptions rather than simply reproducing the previous communications arrangement. The reported result was that the previous communications interruptions were addressed, supporting the intended longer-term protection of service reliability.

Additional safety and emergency functions

Additional safety and emergency functions were introduced alongside the replacement operating controls. These functions addressed a distinct aspect of the passenger application: control arrangements must account for abnormal and emergency conditions as well as routine operation. Their introduction accompanied the project’s requirement for a replacement system meeting current functional safety requirements.

Delivery & Approval

Control-system work within the restoration programme

MJR delivered the electrical and control-system work as part of the wider restoration programme, following its engagement by Rapid Consulting to design and construct the replacement equipment. The delivery brought the new operating controls, operator interface and tram communications into the existing installation.

The new arrangements were integrated into the existing water-balanced tramway. This placed the control-system replacement within the restoration of the retained passenger asset, which reopened to passengers in September 2024.

Technical Summary

  1. Asset and application: Saltburn Cliff Tramway; historic water-balanced passenger funicular.
  1. Location: Saltburn-by-the-Sea, North Yorkshire, UK.
  1. Project scope: System upgrade involving replacement control equipment designed and constructed by MJR for Rapid Consulting.
  1. Control stations: Five: upper station, lower station, main control panel, Saltburn tram control panel and Marske tram control panel; required to operate as one coordinated system.
  1. Control and operator interface: PLC-based operation with a graphical operator console.
  1. Tram communications: Industrial WiFi communications to both trams, replacing the older unreliable radio link.
  1. Safety requirement and functions: Replacement system required to meet current functional safety requirements; additional safety and emergency functions introduced.
  1. Integration: New control arrangements integrated into the existing water-balanced tramway as part of the wider restoration programme.

Project Outcomes

Passenger service restored with modernised controls

The tramway reopened to passengers in September 2024, eight months after the fire. MJR’s electrical and control-system contribution formed part of the wider restoration that returned the water-balanced passenger funicular to service.

At reopening, the restored tramway had modernised controls, improved operator visibility and enhanced safety and emergency functions. These were delivered changes to the operating arrangement, combining replacement of the damaged equipment with an updated operator interface and additional functions.

Previous communications interruptions addressed

Industrial WiFi addressed the previous communications interruptions associated with the older radio link. Protecting the reliability of the local transport service and visitor attraction was the intended longer-term benefit of that replacement, alongside the immediate restoration of passenger operation.

Table of contents
Planning a vessel automation project?

Share your vessel, equipment and interface requirements with MJR.

Related Services

Services to Support Your Project

From marine electrical design consultancy and engineering through construction, installation, commissioning, repair and testing, MJR supports the complete project lifecycle for newbuild, retrofit and upgrade projects.

product-image
Consultancy & Design

Marine electrical design, FEED studies, calculations and system engineering developed around vessel, offshore and project requirements.

product-image
Installation & Commissioning

Marine electrical installation, onboard integration, vessel commissioning and functional testing through to technical handover.

product-image
Engineering & Construction

Integrated electrical power, switchboard, control and automation systems engineered, built and tested for demanding marine and offshore applications.

Related Solutions

Solutions for Your Operational Needs

Follow MJR project updates, company news and technical insight covering marine electrical engineering, automation, shore power, offshore vessel charging and vessel electrification.

solution-images
Automation & Control

Marine automation systems integrating PLC, DCS, HMI, alarm monitoring, data logging, power management and vessel or offshore control.

Related Sectors

Sectors we are Powering

Follow MJR project updates, company news and technical insight covering marine electrical engineering, automation, shore power, offshore vessel charging and vessel electrification.

solution-images
Shipyards and Newbuilds

Show how MJR designs, installs, commissions and supports product systems.

Related Projects

Relevant Project Experience

Explore MJR projects involving vessel automation, monitoring, control and power management across newbuild, retrofit and upgrade programmes.

No items found.
FAQ

Project questions

Questions and answers about Saltburn Tramway Controls.

What is a water-balanced funicular, and what did this project replace?

Which five control stations had to operate together?

What purpose did PLC-based operation serve?

Why was a graphical operator console included?

Why were the previous radio communications replaced with industrial WiFi?

How did safety feature in the control-system replacement?

What work did MJR undertake for Rapid Consulting?

When did the tramway reopen, and what changes were reported?