Project Overview

Lifecycle servicing around an active vessel programme

Subsea 7 required preventative maintenance of ABB ACS800 drives and a comprehensive electrical healthcare survey aboard Seven Borealis, its pipelay and heavy-lift construction vessel. The survey supported the vessel’s five-year DNV class renewal, while the drive work addressed lifecycle maintenance requirements for crane and tensioner equipment.

MJR delivered the work through an international maintenance programme covering locations including Abu Dhabi, South Africa and Barbados. The combined scope brought drive servicing together with inspection, testing and certification support for the vessel’s high- and low-voltage generation and distribution systems, with much of the work undertaken during transit.

Project significance

Fitting lifecycle maintenance and class-renewal support around vessel operations limited additional downtime while providing serviced equipment and condition information for continued operation and future maintenance planning.

The Challenge

Maintenance within an active construction schedule

The maintenance programme had to fit around an active international offshore construction schedule. Work on the crane and tensioner drives therefore needed to be organised around vessel movements, rather than treated as a standalone maintenance period. Removing, overhauling and reinstalling drive modules during voyages made the transit windows an important part of the delivery approach.

Coordinating lifecycle servicing with vessel-wide inspection

The requirement extended beyond the ABB ACS800 drives to the generation, distribution and rotating machinery covered by the electrical healthcare survey. The programme needed to accommodate both equipment servicing and inspection across 6.6kV and 440/230V systems, protection relays and breakers. These were distinct maintenance and assessment tasks serving a common objective: supporting lifecycle requirements and the five-year DNV class renewal.

Scope of Work

Drive servicing and electrical condition assessment

MJR delivered two work packages: ABB drive lifecycle servicing for crane and tensioner equipment, and vessel-wide electrical inspection, testing and certification support.

  • ABB ACS800 drive maintenance, including module removal, overhaul and reinstallation, with replacement of ageing electrical components, cooling fans and heat exchangers.
  • Inspection and testing of high- and low-voltage generation and distribution systems, covering 6.6kV and 440/230V systems, protection relays, breakers and rotating machinery.
  • Survey coverage of six main alternators, one emergency generator and seven thruster motors.
  • Software backups, insulation resistance testing, milliohm testing, relay secondary injection and cooling-system checks.
  • Cooling-system flushing, refilling and pressure testing, together with electrical condition reporting.

Solutions Delivered

Age-based drive component replacement

The drive maintenance used ABB six-year and nine-year preventative maintenance kits. Work included replacing ageing electrical components, cooling fans and heat exchangers within the crane and tensioner drive scope. This addressed the stated lifecycle maintenance requirement through component replacement, rather than limiting the intervention to inspection alone.

Module overhaul during vessel transits

ABB drive modules were removed, overhauled and reinstalled during voyages. Scheduling much of this work during transit made use of vessel movements already within the operating programme, rather than relying on additional time alongside. This delivery method linked the physical overhaul work to the principal operational constraint and helped limit additional vessel downtime.

Cooling-system servicing alongside drive maintenance

Cooling systems were flushed, refilled and pressure-tested, with cooling-system checks also included in the programme. Alongside the replacement of cooling fans and heat exchangers, these activities addressed cooling as a distinct part of the maintenance scope. Cooling removes heat generated during drive operation; servicing its components and fluid circuits therefore complements work on the electrical equipment.

Complementary electrical assessment methods

The healthcare survey combined insulation resistance testing, milliohm testing and relay secondary injection across its electrical inspection scope. These methods address different assessment needs: insulation resistance testing assesses insulation condition, milliohm testing measures very low electrical resistance, and secondary injection checks protection-relay response using injected test signals. Together with equipment inspections, the activities supported condition reporting and the class-renewal maintenance programme.

Delivery & Approval

Execution across transits and dry dock

Engineering teams worked across six countries and four vessel transits, with the programme also including a 14-day dry dock in Abu Dhabi. Much of the work was scheduled during transit rather than additional time alongside, accommodating maintenance within the vessel’s active international construction programme.

During voyages, ABB drive modules were removed, overhauled and reinstalled. Delivery activities included software backups, insulation resistance testing, milliohm testing, relay secondary injection and cooling-system checks. Cooling systems were also flushed, refilled and pressure-tested. The combined programme delivered serviced drive equipment, completed electrical inspections and condition reporting in support of the maintenance and class-renewal requirements.

Technical Summary

  1. Client and asset: Subsea 7’s Seven Borealis, a pipelay and heavy-lift construction vessel.
  1. Delivery footprint: International delivery across six countries, including locations in Abu Dhabi, South Africa and Barbados; four vessel transits and a 14-day dry dock in Abu Dhabi.
  1. Drive application: Preventative maintenance of ABB ACS800 drives serving crane and tensioner equipment.
  1. Lifecycle servicing: ABB six-year and nine-year preventative maintenance kits; replacement of ageing electrical components, cooling fans and heat exchangers.
  1. Overhaul method: Drive modules removed, overhauled and reinstalled during voyages; much of the work scheduled during transit rather than additional time alongside.
  1. Electrical survey coverage: High- and low-voltage generation and distribution systems, including 6.6kV and 440/230V systems, protection relays, breakers and rotating machinery.
  1. Surveyed machinery: Six main alternators, one emergency generator and seven thruster motors.
  1. Software and electrical activities: Software backups, insulation resistance testing, milliohm testing and relay secondary injection.
  1. Cooling maintenance: Cooling-system checks, flushing, refilling and pressure testing.
  1. Renewal and maintenance purpose: Electrical inspection, testing and certification support for the vessel’s five-year DNV class renewal, alongside ABB lifecycle maintenance requirements.

Project Outcomes

Serviced equipment and completed condition assessment

MJR delivered serviced drive equipment, completed electrical inspections and condition reporting. The work supported DNV class renewal and ABB lifecycle maintenance requirements while limiting additional vessel downtime. Undertaking much of the work during transit allowed maintenance activity to fit around the vessel’s operating programme rather than depend solely on additional time alongside.

A basis for continued operation and maintenance planning

The serviced equipment and electrical condition information provided a basis for continued reliable operation and future maintenance planning. The value of the combined programme lay in addressing drive lifecycle needs while assessing the wider electrical systems: equipment maintenance and condition reporting together supported decisions about ongoing care of the vessel’s electrical assets.

Table of contents
Planning a vessel automation project?

Share your vessel, equipment and interface requirements with MJR.

Related Services

Services to Support Your Project

From marine electrical design consultancy and engineering through construction, installation, commissioning, repair and testing, MJR supports the complete project lifecycle for newbuild, retrofit and upgrade projects.

product-image
Service, Repair & Testing

Marine electrical service, fault-finding, repair, testing, retrofit and lifecycle support for vessels and offshore assets.

product-image
Engineering & Construction

Integrated electrical power, switchboard, control and automation systems engineered, built and tested for demanding marine and offshore applications.

product-image
Installation & Commissioning

Marine electrical installation, onboard integration, vessel commissioning and functional testing through to technical handover.

Related Solutions

Solutions for Your Operational Needs

Follow MJR project updates, company news and technical insight covering marine electrical engineering, automation, shore power, offshore vessel charging and vessel electrification.

solution-images
Power Generation & Distribution

Marine power distribution systems covering generation, switchboards, power management systems, load sharing, protection and electrical distribution.

Related Sectors

Sectors we are Powering

Follow MJR project updates, company news and technical insight covering marine electrical engineering, automation, shore power, offshore vessel charging and vessel electrification.

solution-images
Offshore Construction & Subsea

Show how MJR designs, installs, commissions and supports product systems.

Related Projects

Relevant Project Experience

Explore MJR projects involving vessel automation, monitoring, control and power management across newbuild, retrofit and upgrade programmes.

No items found.
FAQ

Project questions

Questions and answers about Seven Borealis Electrical Maintenance.

What equipment did the ABB ACS800 drive maintenance cover?

Which preventative maintenance kits were used?

How did voyage-based module overhaul fit the vessel’s operating schedule?

Why was cooling-system servicing part of the work?

Which electrical systems and machinery did the healthcare survey cover?

What were the purposes of the electrical test methods used?

How extensive was the international delivery programme?

What did the completed maintenance and survey programme provide?