Project Overview

MJR Power & Automation delivers HydroPlow Mobilisation on Prysmian's Monna Lisa

Deck and below-deck power distribution, step-down transformers and HPU supplies, installed at the Port of Middlesbrough ahead of the vessel's next cable-laying campaign.

Monna Lisa operates as part of Prysmian Group's fleet, equipped for complex offshore cable installation, trenching and burial in support of major interconnector and offshore wind projects.

Prysmian Group contracted MJR Power & Automation to carry out the electrical installation required to mobilise a HydroPlow spread aboard her. The HydroPlow lays and buries cable in a single pass — one operation instead of two, which is where the time and cost saving in cable installation comes from, and which places a set of specific demands on the vessel's power.

The work was carried out at the Port of Middlesbrough, Steel River Quay, and covered the provision and integration of power distribution systems supporting the spread both below deck and on deck.

Project significance A plough spread arrives as a collection of separate items - the plough itself, its umbilical winch and hydraulic power unit, a control van, a deck shelter. None of them is useful until it is powered, and none of them was designed around this particular vessel's electrical system. The mobilisation is the work of making them one installation.

The challenge

Several separate items, one electrical system.

The plough's umbilical winch hydraulic power unit, the control van and the deck shelter all needed supply, each with its own requirements, none of them originally matched to this vessel.

Both below deck and on deck.

The distribution had to reach equipment in the machinery spaces and equipment exposed on the working deck, with the routing, containment and penetrations that implies.

Voltages the vessel did not already provide.

Additional 230V supplies were required for the spread, which meant step-down transformers rather than simply extending existing distribution.

A fixed sailing date.

The mobilisation was completed ahead of the vessel's next cable-laying campaign, so the work was bounded by the date she was due to sail rather than by the scope itself.

Scope of Work

Turnkey Vessel Electrical Installation for the HydroPlow Spread

The mobilisation included:

  • Power supply to the control van, deck shelter and umbilical winch hydraulic power unit for the plough
  • Installation of 230V and 440V distribution boards for the additional deck equipment
  • Installation of a 25kVA 440V/230V transformer for the additional 230V supplies
  • Installation of three stainless steel junction boxes, to the client's specification

Scope of work:

  • Power distribution, installation and termination across the vessel's MV, 440V and 230V networks
  • Design, build, installation and commissioning of deck power distribution systems
  • Integration of transformers for step-down supply to 230VAC networks
  • Cable management design and installation, including design of new ladder racks and cable penetrations
  • Installation of deck equipment, including hydraulic power units for the HydroPlow

Solutions Delivered

The Distribution — New boards for new equipment

230V and 440V distribution boards were installed to serve the additional deck equipment, designed, built, installed and commissioned as part of the scope rather than adapted from what was already aboard. Cable management was designed alongside them, including new ladder racks and cable penetrations for the routes the spread required.

The Transformers — Supplies the vessel did not have

Step-down transformers were integrated to provide the additional 230VAC supplies the spread needed, taking 440V from the vessel's existing distribution and delivering it at the voltage the mobilised equipment required.

The Plough Spread — Powering each element

Supplies were provided to the control van from which the plough is operated, the deck shelter, and the hydraulic power unit driving the umbilical winch. The HPUs for the HydroPlow were installed as part of the deck equipment scope.

The HydroPlow lays and buries cable simultaneously. Everything above exists so that a single pass does the work of two, which is what makes the spread worth mobilising in the first place.

The Detail — Stainless steel junction boxes to specification

Three stainless steel junction boxes were installed to the client's specification. It is a small item and it is worth keeping, because it shows a client with a view on how the work should be done and a contractor building to it rather than to their own standard.

Delivery & Approval

Completed to Client Specification at Steel River Quay

All installations were completed to the client's specifications, supporting safe and efficient operation of the HydroPlow system. The electrical infrastructure delivered reliable power distribution across all HydroPlow components, and the mobilisation was completed ahead of Monna Lisa's next cable-laying campaign.

Technical Summary

  • Client Prysmian Group.
  • Vessel Monna Lisa — cable installation, trenching and burial vessel
  • Vessel role Interconnector and offshore wind cable projects
  • Sector Offshore Wind; Offshore Construction & Subsea
  • Spread mobilised HydroPlow — simultaneous cable lay and burial
  • MJR scope Turnkey vessel electrical installation for the mobilisation
  • Location Port of Middlesbrough, Steel River Quay
  • Distribution boards 230V and 440V, for additional deck equipment
  • Transformers 25kVA 440V/230V
  • Supplies provided Control van; deck shelter; umbilical winch HPU
  • Deck equipment HPUs for the HydroPlow
  • Cable management New ladder racks and cable penetrations, designed and installed
  • Additional Three stainless steel junction boxes to client specification
  • Coverage Three stainless steel junction boxes to client specification
  • Coverage Below deck and on deck

Project Outcomes

The HydroPlow spread fully supplied

Reliable power distribution across every component of the spread — plough, umbilical winch HPU, control van and deck shelter.

Completed ahead of the campaign

The mobilisation was finished before the vessel's next cable-laying campaign, which is the only deadline that matters on work of this kind.

Built to the client's specification

Including the detail items, delivered as the client wanted them rather than as the contractor would have chosen.

New distribution capability retained aboard

Distribution boards, transformers, ladder racks and penetrations remain on the vessel, so future mobilisations start from a better position than this one did.

A third Prysmian vessel

Following the Ulisee and Barbarossa I, and against a stated history of multiple earlier mobilisations.

Table of contents
Planning a vessel automation project?

Share your vessel, equipment and interface requirements with MJR.

Related Services

Services to Support Your Project

From marine electrical design consultancy and engineering through construction, installation, commissioning, repair and testing, MJR supports the complete project lifecycle for newbuild, retrofit and upgrade projects.

product-image
Consultancy & Design

Marine electrical design, FEED studies, calculations and system engineering developed around vessel, offshore and project requirements.

product-image
Engineering & Construction

Integrated electrical power, switchboard, control and automation systems engineered, built and tested for demanding marine and offshore applications.

product-image
Installation & Commissioning

Marine electrical installation, onboard integration, vessel commissioning and functional testing through to technical handover.

product-image
Service, Repair & Testing

Marine electrical service, fault-finding, repair, testing, retrofit and lifecycle support for vessels and offshore assets.

Related Solutions

Solutions for Your Operational Needs

Follow MJR project updates, company news and technical insight covering marine electrical engineering, automation, shore power, offshore vessel charging and vessel electrification.

solution-images
Power Generation & Distribution

Marine power distribution systems covering generation, switchboards, power management systems, load sharing, protection and electrical distribution.

solution-images
Subsea Power & Control Systems

Integrated subsea power and control systems for ROVs, trenchers, ploughs, cable-lay equipment and specialist offshore and subsea machinery.

Related Sectors

Sectors we are Powering

Follow MJR project updates, company news and technical insight covering marine electrical engineering, automation, shore power, offshore vessel charging and vessel electrification.

solution-images
Offshore Wind

Show how MJR designs, installs, commissions and supports product systems.

solution-images
Offshore Construction & Subsea

Show how MJR designs, installs, commissions and supports product systems.

Related Projects

Relevant Project Experience

Explore MJR projects involving vessel automation, monitoring, control and power management across newbuild, retrofit and upgrade programmes.

archive-single-image

Mobilisation of Deck Equipment and Trenching Spreads — Three Ports, Two Countries

archive-single-image

Electrical Installation for an Active Heave Compensated Crane — Across Three Countries

archive-single-image

Electrical Mobilisation of the World's Most Powerful Subsea Trencher

FAQ

The Questions We Get Asked Most

Find answers to common questions about the project, including the systems involved, engineering approach, technical challenges and how the solution was delivered.

What does mobilising a cable plough spread involve electrically?

Why does a mobilised spread need its own distribution boards?

What is a HydroPlow?

Can the same spread be mobilised onto a different vessel later?

Do you design the cable management as well as install it?

Can you build to our own specification?

Do you install hydraulic power units and other deck equipment?

Do you work for cable installation contractors as well as vessel owners?